WMS implementation plan and go-live checklist

Most WMS project problems come not from the software but from unprepared data, incomplete testing and a rushed go-live. This plan is a framework to assess the vendor's plan and track your own side of the work.

Last updated: 2026-09-19

Project phases

Durations vary with scope, number of sites and integrations. Ask the vendor for a plan per phase with durations, deliverables and the resources expected from you.

PhaseKey activitiesDeliverableOwner
1. MobilisationProject team, governance, communication plan, risk logProject charterCustomer + vendor
2. Analysis and designProcess workshops, exceptions, location structure, labels, integration interfacesSigned-off solution design (scope document)Vendor, customer sign-off
3. Configuration and buildSystem rules, reports, custom developments, integrationsWorking system in the test environmentVendor
4. TestingUnit, integration, user acceptance (UAT) and load testsSigned UAT report, open defect listCustomer (UAT), vendor
5. Data migrationItem master, locations, opening stock, open orders; trial loadsValidated data loadCustomer (data), vendor (tools)
6. TrainingKey-user training, operator training, manualsTraining recordsVendor + key users
7. Go-liveGo / no-go decision, stock count, cut-over, on-site supportLive systemJoint
8. HypercareIntensive support, daily stand-ups, KPI tracking, closureProject closure reportJoint

Customer-side responsibilities

Test plan

Go-live (go / no-go) checklist

Make the go-live decision against this list, not the calendar. Assign an owner and evidence to each item.

Hypercare